RIPEN Utility Services
has been awarded the project management of SP AusNet's
$12M Traralgon
66/22kV zone substation upgrade, as well as $6M
Leongatha ZZS Stage 2 Redevelopment and Sale ZSS
Stage 1 Redevelopment projects.
Included
below are details of some of the projects currently being undertaken
or recently completed by RIPEN Utility Services:
SP AusNet Traralgon
66/22kV Zone Substation Rebuild Stage 1
RIPEN Utility
Services have been engaged by SP AusNet to project manage the $12M
stage 1 redevelopment of the Traralgon 66/22kV zone substation,
together with Stage 2 of Leongatha redevelopment and Stage 1 of Sale
zone substation rebuilds.
Ridley Agriproducts
RIPEN Utility
Services have recently completed a motor starting and Distribution
Code compliance study for proposed expansion activities at Ridley
Agriproducts in Pakenham.
SP AusNet Leongatha
66/22kV Zone Substation Rebuild Stage 1
RIPEN Utility
Services have been engaged by SP AusNet to project manage the $10.2M
stage 1 redevelopment of the Leongatha 66/22kV zone substation.
SP AusNet 22kV Feeder
Reliability Reviews
Over the past 18 months, RIPEN Utility
Services have been undertaking 22kV feeder reliability assessments
for SP AusNet, including the development of solutions and general
reliability strategies and implementation policies.
Castella Quarries
RIPEN Utility Services
have recently completed a third stage development assessment of motor starting solutions
for proposed new crushing and processing equipment at Castella
Quarries. The assessment undertaken involved the predictive modelling of motor starting effects on the 22kV network in
accordance with relevant Australian Standards.
T Squared/Tenix
Alliance Zone Substation Cable Ratings & Summer Contingency Plans
RIPEN
Utility Services have recently completed an assessment of 22kV
feeder exit cable ratings for numerous heavily loaded SP AusNet
feeders in areas of high load growth. Additionally, RUS were
engaged to prepare summer contingency plans for various zone
substations, to identify load transfer opportunities, risk
management strategies etc, in the event of critical asset failures
over the summer period.
SP AusNet Northern
Growth Corridor Load Management Study
RIPEN
Utility Services have recently completed a significant load management
study within the Melbourne Northern Growth Corridor in areas residing in
SP AusNet's distribution business. The study determined a
range of load management initiatives/measures to assist T Squared/SP
AusNet in
the management of network loading, during a period of extensive
network augmentation and development and high customer load growth.
Copyright 2012 RIPEN
Utility Services
Ph: 0408-057-034 PO Box 993, TRARALGON,
Victoria, Australia, 3844